Dome construction, setting of centre pipe, turret, treatment of gas holder/top dome, Construction of outlet passage and hydraulic chamber and Construction of inlet and setting of mixing device

After completing the wall, construction of the top dome starts. The top dome is a brick masonry work and can be done easily by providing a framework. But this is a costly solution. The masonry work can be done using Chinese method.
At first, the centre of the top dome curvature is identified and is fixed by constructing a temporary brick pillar. A bamboo stick of size p1 is taken. One end of the stick is set at the centre and the other end is moved to determine the position of the bricks. Bricks are laid one by one and retained by using GI wire hooks and supports of bricks as shown in the figure. After completing one layer, at least 8 hours is allowed to set the mortar, after which all the hooks are taken away and second layer is laid. Thus the whole dome is completed.
When the dome is completed, there will be a hole at the centre that cannot be finished with bricks. This should be covered with cement concrete. During casting of cement concrete, the centre pipe is to be set in it. Usually, the length of the centre pipe is 60 cm having a clamp at the bottom and a reducer pipe at the top. In order to protect the centre pipe from external shock, a turret measuring 36cmx36cmx40cm and made of bricks is provided.
Treatment of gas holder/top dome
Dome construction is a critical stage of whole plant. In case of negligence, dome may have gas leakage which can not be recovered with minor maintenance. Therefore, dome treatment has to be given high attention. Inner surface of the digester can be divided into two parts. The lower portion acts as digester, whereas the upper part acts both as digester and gas holder. So, special attention should be given to the treatment of the gasholder. The lower part up to the bottom of the lintel is to be finished with cement plaster in a conventional way. To make the upper part air tight, the treatment is done in 4 layers as shown in the estimate and drawing. In the first and second layer, cement grouting is to be applied before plastering.
Gas tightness in the dome is highly important while constructing plant. Therefore, constructors have to be careful on possible leakage and have to check the leakage after construction. There are two methods suggested to check the leakage.
a)    Fill the digester with water after construction and treatment of dome and observe for two days whether water level is going down or not. If water level is going down then you suspect gas leakage.
b)    Once filled the plant with dung and starting gas formation, put layer of soap on top of the dome and see whether any bubbles are coming out. If bubbles are seen then the gas is leaking from that part.
If gas leakage is discovered, do the treatment again and make sure that the dome is gas tight.
Construction of outlet passage and hydraulic chamber
Construction of outlet passage and hydraulic chamber should be done at the same time the digester wall is constructed. Care should be taken about the level of the outlet pipe. The bottom of the outlet pipe should be at least 7.5cm lower than the bed of the inlet. After completion of the hydraulic chamber, long time is taken in constructing the slab. It is therefore suggested that, the slab of the hydraulic chamber should be cast during the casting of the bottom dome.

Construction of inlet and setting of mixing device
Inlet with proper mixing device is important. Mix the dung with water properly which will help producing more gas. Mixing device should be set during construction. In case of poultry litter, the inlet pipe should be raised a bit high providing small holes in the exposed portion of the pipe so that water does not stand in the inlet. Care should be taken to the issue that, inlet should be at least 7.5 cm higher that the bottom of the overflow pipe.