Digging pits
Digging of the digester shall be started after completion of the layout. Following digging up to the bottom of the hydraulic chamber, layout of outdoor passage shall be given as per drawing under para 3.4. At this stage, earthwork in the digester and outdoor passage will be continued up to the bottom level of the outdoor passage.
Thereafter, a long straight bamboo pole shall be fixed at the centre of the digester C2 and the point shall be lowered down to a depth of curved bottom dome. Mark the centre of the bottom dome curvature on the pole at a distance of p2 from the bottom. Take a rope of size p2. Fix one end of the rope at the centre, move the other end and complete the earthwork of the bottom dome. Ram the bed well with a rammer.
Casting of bottom dome and outlet passage bottom
After completion of earthwork, lay a thin layer of polythene on the bed. Set some concrete blocks of height 7.5cm and complete casting of bottom dome and the bed of the outlet passage. The ratio of cement, sand and aggregate should be 1:3:6.
Construction of digester and outlet passage wall
Take a bamboo stick of length D2/2. Fix one end of the stick to the bamboo pole. Move the other end and determine the space to be kept. Start the work of digester wall and also the wall of the outlet passage. Keep a gap of 75cm in the digester wall for outlet passage door. The outlet passage will be 75cmx75cm size. Cement mortar should be a ratio of 1:3.
Setting of inlet pipe
When digester wall is raised up to a height of 30cm, it shall be stopped. At this stage the inlet pipe shall be set as shown in the drawing. One end of the pipe will rest on the wall and the other end shall be placed at an angle of 30ยบ.
Casting of lintel
After raising the wall to a height of h7, a lintel is to be constructed on the gap/ door kept for the outlet passage as per drawing in figure-6. It is suggested to cast the lintel on the ground during bed casting and place on the gap at this stage. This will save both time and cost. After setting of lintel, wall construction will continue and rise up to a height of h2+h3 from the floor of the outlet passage.
Digging of the digester shall be started after completion of the layout. Following digging up to the bottom of the hydraulic chamber, layout of outdoor passage shall be given as per drawing under para 3.4. At this stage, earthwork in the digester and outdoor passage will be continued up to the bottom level of the outdoor passage.
Thereafter, a long straight bamboo pole shall be fixed at the centre of the digester C2 and the point shall be lowered down to a depth of curved bottom dome. Mark the centre of the bottom dome curvature on the pole at a distance of p2 from the bottom. Take a rope of size p2. Fix one end of the rope at the centre, move the other end and complete the earthwork of the bottom dome. Ram the bed well with a rammer.
Casting of bottom dome and outlet passage bottom
After completion of earthwork, lay a thin layer of polythene on the bed. Set some concrete blocks of height 7.5cm and complete casting of bottom dome and the bed of the outlet passage. The ratio of cement, sand and aggregate should be 1:3:6.
Construction of digester and outlet passage wall
Take a bamboo stick of length D2/2. Fix one end of the stick to the bamboo pole. Move the other end and determine the space to be kept. Start the work of digester wall and also the wall of the outlet passage. Keep a gap of 75cm in the digester wall for outlet passage door. The outlet passage will be 75cmx75cm size. Cement mortar should be a ratio of 1:3.
Setting of inlet pipe
When digester wall is raised up to a height of 30cm, it shall be stopped. At this stage the inlet pipe shall be set as shown in the drawing. One end of the pipe will rest on the wall and the other end shall be placed at an angle of 30ยบ.
Casting of lintel
After raising the wall to a height of h7, a lintel is to be constructed on the gap/ door kept for the outlet passage as per drawing in figure-6. It is suggested to cast the lintel on the ground during bed casting and place on the gap at this stage. This will save both time and cost. After setting of lintel, wall construction will continue and rise up to a height of h2+h3 from the floor of the outlet passage.