Session plan for Developing and Operationalizing Participatory Monitoring and Evaluation (PM&E )System

 The Session plan for Developing and Operationalizing Participatory Monitoring and Evaluation (PM&E ) System:
Goal:    To describe participants the summary steps involved in developing and implementing the PM&E
system for a project.

Objectives:    By the end or completion of this session, the training beneficiaries or participants will be enough able to:
1.    Identify the steps involved in designing a PM&E system.
2.    Identify key activities and resources required in each step in designing PM&E.
3.    Describe the preparation and actions to be taken for operationalyzing PM&E system.

Duration:     1 hour 30 minutes

Methods:    Group Discussion, Mobile Plenary and Brainstorming

Materials:    Transparency (TS):    4.5.1

Handout:         4.5.1 – Step to design a PM&E system
            4.5.2 – The organization and operationalization of project PM&E
   
Facilitator Preparation:       
In preparing for this session, the facilitator(s) will ready the TS and read the handouts minutely to gain overall idea about the subject matter of discussion.

Process:    Step I: Defining Objective of this Session (5 min)
   
Explain participants that sufficient discussions have been made by this time on designing PM&E system of a project. In this session they will summarize the steps involve in designing PM&E system and identify the activities and support required in each step. This will help participants in conceptualizing the entire process of designing PM&E system better and remove ambiguities, if there is any.

Step II: Identifying the Steps involve in Designing PM&E System (15 min)

Ask participants to write on their writing pad all the steps involve in designing a PM&E system for a development project, based on discussion so far made in this training course. Give some time to the participants to think and write the steps.

After the given time, ask participants to read the steps that they written on their pad. Listen to participants as many as possible. Now you read the steps provided in the Handout 4.5.1 randomly (not sequentially, because in the next step – participants will work on sequencing the steps) and ask participants to see if all the steps you read are identified by them. If not, ask them to include the step in the note.

Step III: Sequencing the Steps involve in Designing PM&E System (25 min)
Ask participants to stand in a circle in the middle of the classroom. Put the puzzle card set prepared on the steps of designing PM&E system following the TS 4.5.1 in the middle of the circle. Ask some participants to arrange the cards in sequential order and instruct others to watch the arrangement. However, they can involve in arranging cards, if they feel the sequence is not going in correct orders. When the participants, as per their own idea finish the arrangement of cards, ask them to take seat and see the correct sequence of arrangement that you will show them by transparency. Show the TS 4.5.1 and ask participants to compare their arrangement of the puzzle cards with the one you shown in the transparency and identify where they lost the sequence. Explain each step in short to summarize the entire process once more.

Step IV: Identifying Key Activities and Support Required in Each Step (30 min)

Explain participants that they need to identify now the key activities and support required in each step of designing PM&E system. Post 10 flip chart paper- one flip chart for each step, at different places in the classroom and write a step’s name on the top of each flip chart paper. Ask participants to move around the flip chart papers and write key activities and support required in each step. Explain participants that this is a mobile plenary method, so all the participants should not gathered under one flip chart paper at a time, rather under different flip chart paper.

When the participants finish writing, instruct them to review and read each of the flip chart papers. Ask participants to remain careful during review of the flip chart papers, to see if any key activity is missing.

Step V: Preparation and Actions Required Implementing the PM&E System (15 min)

Brainstorm participants to mention about preparation and actions required in implementing a PM&E system. Write the points mentioned by participants on a flip chart paper. Revisit and analyze the points, keeping the relevant points and remove the irrelevant ones and prepare a summary list on preparation and actions required for implementing a PM&E system. Finally conclude the session with the distribution of Handout 4.5.1 & 4.5.2 to the participants.