Session Plan on Selecting Planning, Monitoring & Evaluation (PM&E) Indicators for each Area of a Project
Goal: To orient participants about indicators, their types and selection process.
Objectives of the session: By the end or just after completion of this session, the participants will be enough
capable of able to:
1. Define the term ‘Indicator’.
2. Explain different types of Indicators.
3. Select Indicators for different monitoring areas of a project.
Duration: 1 hour 45 minutes
Methods: Group Discussion, Case study, and Small Group Works
Materials: Transparency (TS):
Handout: 4.3.1 – Case Study “Sanitation & Hygiene Project of IKRA”
4.3.2 – PM&E Planning Matrix
4.3.3 - Indicators
Facilitator Preparation:
Facilitator(s) will ready the TS that will be used in this session and read the case studies deeply. S/he will also read the handouts used in this session mindfully to gain a through understanding on indicators, their types and selection process.
Process: Step I: Defining Indicators and their Types (30 min)
Explain participants that after identifying the broad monitoring areas of a project, the next step is to identify and select indicators in each area on which data will be collected from the field. Before going to identify the indicators, ask participants to define what they understand by the term ‘Indicator’. Give one ZOPP card to each participant and ask to write the definition of an indicator on the card. Ask participants to post the written card on the VIPP board. Read the cards one by one, remove very irrelevant cards and explain the correct ones. Show TS 4.3.1 and define the indicator further to develop better understanding among participants.
Now explain different types of indicators showing TS. Mention that in program monitoring, indicators are of five different types:
• Input Indicators
• Activity Indicators
• Outputs Indicators
• Effect Indicators
• Impact Indicators
In another way, the indicators are classified into two broad categories:
• Aggregate Indicators
• Operational Indicators
Explain each category of indicators with examples. Also explain that all these indicators are related to the program monitoring. For developing a complete M&E system, indicators should also be identified for other areas of a project like – staff, procurement, budget, etc. Remind participants that in developing a participatory M&E system, involvement of community peoples in indicator selection must be ensured.
Step III: Identifying Indicators (60 min)
Inform participants that in this step they will work in small groups to develop detail list of indicators at ‘Activity’ and ‘Output’ levels based on a case study. Divide participants into four small groups and distribute the case study - Handout 4.3.1. Also distribute Handout 4.3.2 – M&E Planning Matrix to each small group. Ask participants in each small group to read the case study and fill up the column (1), (2) and (3) of the M&E Planning Matrix (Handout 4.1.3) using the information from the case study. Ask small group to prepare the M&E Planning Matrix in large flip chart paper for presentation purpose. Allow small groups 40 – 45 minutes to identify the indicators and data to be collected against each indicator.
At the end of give time, ask small groups to merge into large group and present their findings. When the small groups are presenting their findings, review those carefully and provide necessary comments and suggestions. Finally conclude the sessions with the distribution of Handout.
Goal: To orient participants about indicators, their types and selection process.
Objectives of the session: By the end or just after completion of this session, the participants will be enough
capable of able to:
1. Define the term ‘Indicator’.
2. Explain different types of Indicators.
3. Select Indicators for different monitoring areas of a project.
Duration: 1 hour 45 minutes
Methods: Group Discussion, Case study, and Small Group Works
Materials: Transparency (TS):
Handout: 4.3.1 – Case Study “Sanitation & Hygiene Project of IKRA”
4.3.2 – PM&E Planning Matrix
4.3.3 - Indicators
Facilitator Preparation:
Facilitator(s) will ready the TS that will be used in this session and read the case studies deeply. S/he will also read the handouts used in this session mindfully to gain a through understanding on indicators, their types and selection process.
Process: Step I: Defining Indicators and their Types (30 min)
Explain participants that after identifying the broad monitoring areas of a project, the next step is to identify and select indicators in each area on which data will be collected from the field. Before going to identify the indicators, ask participants to define what they understand by the term ‘Indicator’. Give one ZOPP card to each participant and ask to write the definition of an indicator on the card. Ask participants to post the written card on the VIPP board. Read the cards one by one, remove very irrelevant cards and explain the correct ones. Show TS 4.3.1 and define the indicator further to develop better understanding among participants.
Now explain different types of indicators showing TS. Mention that in program monitoring, indicators are of five different types:
• Input Indicators
• Activity Indicators
• Outputs Indicators
• Effect Indicators
• Impact Indicators
In another way, the indicators are classified into two broad categories:
• Aggregate Indicators
• Operational Indicators
Explain each category of indicators with examples. Also explain that all these indicators are related to the program monitoring. For developing a complete M&E system, indicators should also be identified for other areas of a project like – staff, procurement, budget, etc. Remind participants that in developing a participatory M&E system, involvement of community peoples in indicator selection must be ensured.
Step III: Identifying Indicators (60 min)
Inform participants that in this step they will work in small groups to develop detail list of indicators at ‘Activity’ and ‘Output’ levels based on a case study. Divide participants into four small groups and distribute the case study - Handout 4.3.1. Also distribute Handout 4.3.2 – M&E Planning Matrix to each small group. Ask participants in each small group to read the case study and fill up the column (1), (2) and (3) of the M&E Planning Matrix (Handout 4.1.3) using the information from the case study. Ask small group to prepare the M&E Planning Matrix in large flip chart paper for presentation purpose. Allow small groups 40 – 45 minutes to identify the indicators and data to be collected against each indicator.
At the end of give time, ask small groups to merge into large group and present their findings. When the small groups are presenting their findings, review those carefully and provide necessary comments and suggestions. Finally conclude the sessions with the distribution of Handout.