Development organization SSP is an organization using donor fund from internal donor is reimbursed/transferred from Sonali Bank for the operation of the project. As per mandate of the project, the project expenses are to be audited annually by an independent audit firm. The external auditors will carry out the auditing as per following TOR.
1. Contents, Principal and Duration of the mandate (Scope of the Audit)
1.1- Contents of the Mandate (scope of the audit)
a) Audit of the accounts of the Project in Bangladesh accounted for the period from July 1, 2012 to June 31, 2013 and Employees Provident Fund Account for the same period according to the international auditing standards.
b) Establish an audit plan according to generally accepted auditing standard which includes:
- the type of transactions to be checked and the methods/techniques used;
- The planned physical control and the dates;
- The planned visit to the Rangpur district site;
- Establishing an audit report of the project concerning the relevant points;
- Discussion with SSP Management in regards to obtaining audit information and solving audit problems.
1.2- Principal of the audit
The mandate includes all the points mentioned in point 1.1 with the following audit operations:
a) Check the correctness and completeness of the financial transactions
b) Check whether the accounts are maintained as per financial management manual guideline of the project
c) Check whether last year’s audit remarks, if any, are implemented.
d) Check whether the expenditures are utilized efficiently and effectively.
1.3 – Approach of the Auditee and the Auditor
a) The Auditee shall give the full support and provide all relevant documents to the Auditors.
b) The Auditor should, in addition to the checking approach, provide a strong support to the system and personnel of the project and be confident and reliable partner to the Management.
1.4- Duration of the mandate
The mandate shall have duration of 3 days starting from May’2 date 2013 The period of the audit can be extended by mutual exchange of letters between the parties.
2. Professional Secrecy
a) Any document, information or dates entrusted to or produced by the Auditor in connection with this assignment shall be strictly confidential and cannot be used by the Auditor for any other purpose without the written consent of the Auditee. This provision shall remain valid even after the completion of this assignment.
b) The Auditor shall be liable for and ensure a careful and professional performance of the tasks on behalf of the Auditee.
c) The auditor shall immediately inform the Auditee of any event, which could have a negative influence or endanger the successful completion of the assignment.
3. Obligation to Testify
If during the course of the audit any frauds / misappropriation are detected, the Auditor shall have to provide evidence of the incidence to SSP and the Auditee so that the Auditee can take legal actions, if necessary.
4. Anti- Corruption Clause
Neither party shall either offer a third person or seek, accept or get promised directly on indirectly for himself or any other party any gift or benefits which would or could be construed an illegal practice.
5. Documentation
The following document are considered to be the basis for this audit
Financial rules and regulation of NGOs in Bangladesh.
SEED monthly financial reports to Donor
Financial back-up/support materials
Documents/assessment/reports on Financial Information System
SSP's Financial and Administration Manuals.
6. Description of the details of this mandate
6.1 General Control and Compliance
a) Verification of the receipts of funds and exchange rate.
b) Physical verification of the fixed /mobile assets of the project.
c) Verification of the expenditures and check whether they correspond to the Project Budget.
d) Preparation of the budget variance statement and analysis of the variances.
e) Checking of the internal control system and give comments in the report.
f) Verification of the project transactions are to focus on the following points:
- checking whether the expenditures are fully authorized
- checking the validity of the vouchers and original bills/documents
- checking of all advance accounts and confirm their balances
- checking the applicable taxes, payroll and others
- Checking separation of functions (like cashier and book-keeper) are proper and comment in the report
- Verification of total purchase (local and foreign) and whether the procedures are followed as per Purchase manual/procedures of the comment whether they reflect a fair market price
- Verification of the proper implementation and execution of the audit remarks of the preceding year, if any.
6.2 Special Control/checks
a) Verification of the total project purchases and check whether the procedures are followed as per regulation.
b) Checking the correctness of the booking of all incomes and expenses
c) Checking of all advance accounts and justify the advances which are older than 6 (six) months
d) Checking of deduction for VAT, Taxes etc from payments (where applicable).
e) Checking of the vehicle log books and incorporation of the procedure for private use
f) The Auditor has the right and duty to establish additional/special checks if necessary
7. Reporting of Audit
The Auditor shall submit four copies of the draft version of their audit report and a separate Management report with their comments to SEED within 30 days from the date of acceptance of this mandate. After discussion and acceptance of the daft audit report by the Auditee, the Auditor shall submit !! copies of the final audit report and management report to SEED Management within !! days from the acceptance of the draft audit report.
8. Fees
In accordance with the proposal given by the Auditor, the fee for the Project audit amounts to Tk. 10,000 inclusive of VAT.
The Auditee will pay this fee within a month after receiving the final report. No additional fees will be paid without prior approval and agreement between the Auditor and the Auditee.
9. Termination of the Mandate.
a) This mandate can be terminated by either parties with a written notice within one month from the date of signing this mandate.
b) The Auditee can terminate the contract without any notice in the following circumstances:
- if the Auditor cannot fulfill the Terms of Reference
- if the Auditor cannot submit their reports within the time specified in point 7 of this mandate
- if the Auditor fails to inform the incidence of frauds/misappropriation to the Auditee and SEED or does not mention the incidence of fraud/misappropriation in their audit report.
Accepted by:
Auditor Auditee
Dated Dated
Between
Development organization
Hereinafter referred to as Auditee
And
The firm Hereinafter referred to as Auditor
Development organization SSP is an organization using donor fund from internal donor is reimbursed/transferred from Sonali Bank for the operation of the project. As per mandate of the project, the project expenses are to be audited annually by an independent audit firm. The external auditors will carry out the auditing as per following TOR.
1. Contents, Principal and Duration of the mandate (Scope of the Audit)
1.1- Contents of the Mandate (scope of the audit)
a) Audit of the accounts of the Project in Bangladesh accounted for the period from July 1, 2012 to June 31, 2013 and Employees Provident Fund Account for the same period according to the international auditing standards.
b) Establish an audit plan according to generally accepted auditing standard which includes:
- the type of transactions to be checked and the methods/techniques used;
- The planned physical control and the dates;
- The planned visit to the Rangpur district site;
- Establishing an audit report of the project concerning the relevant points;
- Discussion with SSP Management in regards to obtaining audit information and solving audit problems.
1.2- Principal of the audit
The mandate includes all the points mentioned in point 1.1 with the following audit operations:
a) Check the correctness and completeness of the financial transactions
b) Check whether the accounts are maintained as per financial management manual guideline of the project
c) Check whether last year’s audit remarks, if any, are implemented.
d) Check whether the expenditures are utilized efficiently and effectively.
1.3 – Approach of the Auditee and the Auditor
a) The Auditee shall give the full support and provide all relevant documents to the Auditors.
b) The Auditor should, in addition to the checking approach, provide a strong support to the system and personnel of the project and be confident and reliable partner to the Management.
1.4- Duration of the mandate
The mandate shall have duration of 3 days starting from May’2 date 2013 The period of the audit can be extended by mutual exchange of letters between the parties.
2. Professional Secrecy
a) Any document, information or dates entrusted to or produced by the Auditor in connection with this assignment shall be strictly confidential and cannot be used by the Auditor for any other purpose without the written consent of the Auditee. This provision shall remain valid even after the completion of this assignment.
b) The Auditor shall be liable for and ensure a careful and professional performance of the tasks on behalf of the Auditee.
c) The auditor shall immediately inform the Auditee of any event, which could have a negative influence or endanger the successful completion of the assignment.
3. Obligation to Testify
If during the course of the audit any frauds / misappropriation are detected, the Auditor shall have to provide evidence of the incidence to SSP and the Auditee so that the Auditee can take legal actions, if necessary.
4. Anti- Corruption Clause
Neither party shall either offer a third person or seek, accept or get promised directly on indirectly for himself or any other party any gift or benefits which would or could be construed an illegal practice.
5. Documentation
The following document are considered to be the basis for this audit
Financial rules and regulation of NGOs in Bangladesh.
SEED monthly financial reports to Donor
Financial back-up/support materials
Documents/assessment/reports on Financial Information System
SSP's Financial and Administration Manuals.
6. Description of the details of this mandate
6.1 General Control and Compliance
a) Verification of the receipts of funds and exchange rate.
b) Physical verification of the fixed /mobile assets of the project.
c) Verification of the expenditures and check whether they correspond to the Project Budget.
d) Preparation of the budget variance statement and analysis of the variances.
e) Checking of the internal control system and give comments in the report.
f) Verification of the project transactions are to focus on the following points:
- checking whether the expenditures are fully authorized
- checking the validity of the vouchers and original bills/documents
- checking of all advance accounts and confirm their balances
- checking the applicable taxes, payroll and others
- Checking separation of functions (like cashier and book-keeper) are proper and comment in the report
- Verification of total purchase (local and foreign) and whether the procedures are followed as per Purchase manual/procedures of the comment whether they reflect a fair market price
- Verification of the proper implementation and execution of the audit remarks of the preceding year, if any.
6.2 Special Control/checks
a) Verification of the total project purchases and check whether the procedures are followed as per regulation.
b) Checking the correctness of the booking of all incomes and expenses
c) Checking of all advance accounts and justify the advances which are older than 6 (six) months
d) Checking of deduction for VAT, Taxes etc from payments (where applicable).
e) Checking of the vehicle log books and incorporation of the procedure for private use
f) The Auditor has the right and duty to establish additional/special checks if necessary
7. Reporting of Audit
The Auditor shall submit four copies of the draft version of their audit report and a separate Management report with their comments to SEED within 30 days from the date of acceptance of this mandate. After discussion and acceptance of the daft audit report by the Auditee, the Auditor shall submit !! copies of the final audit report and management report to SEED Management within !! days from the acceptance of the draft audit report.
8. Fees
In accordance with the proposal given by the Auditor, the fee for the Project audit amounts to Tk. 10,000 inclusive of VAT.
The Auditee will pay this fee within a month after receiving the final report. No additional fees will be paid without prior approval and agreement between the Auditor and the Auditee.
9. Termination of the Mandate.
a) This mandate can be terminated by either parties with a written notice within one month from the date of signing this mandate.
b) The Auditee can terminate the contract without any notice in the following circumstances:
- if the Auditor cannot fulfill the Terms of Reference
- if the Auditor cannot submit their reports within the time specified in point 7 of this mandate
- if the Auditor fails to inform the incidence of frauds/misappropriation to the Auditee and SEED or does not mention the incidence of fraud/misappropriation in their audit report.