A Post Flood Emergency Project and it's activities are as follows:
In the mean time, SSP, the development organization implemented another emergency project in the Mithapukur Upazila after the devastating flood 2004 titled as “Post Flood and Community Based Arsenic
Mitigation program/ Project”.
The Duration of this project was 3 (three ) months from December ’04 to March ‘05. The main activities of this project were follows:
o Survey of damages to the ground water sources
o Disinfections of Dug Wells (DWs), Rain Water Harvesters (RWHs) and Shallow Shrouded Tube wells (SSTs).
o Earth filling around platform of DWs, RWHs and SSTs.
o Caretakers training of all DWs.
o Dewatering or de-sanding of dug wells and RWHs.
o Repair of platform, apron and lining of DWs, RWHs and SSTs.
o Raising of platforms and guard wall of the DWs.
o Water quality testing of DWs, RWHs and SSTs.
o Outside plastering of the RWHs.
o Repairing of guttering of RWHs.
In the mean time, SSP, the development organization implemented another emergency project in the Mithapukur Upazila after the devastating flood 2004 titled as “Post Flood and Community Based Arsenic
Mitigation program/ Project”.
The Duration of this project was 3 (three ) months from December ’04 to March ‘05. The main activities of this project were follows:
o Survey of damages to the ground water sources
o Disinfections of Dug Wells (DWs), Rain Water Harvesters (RWHs) and Shallow Shrouded Tube wells (SSTs).
o Earth filling around platform of DWs, RWHs and SSTs.
o Caretakers training of all DWs.
o Dewatering or de-sanding of dug wells and RWHs.
o Repair of platform, apron and lining of DWs, RWHs and SSTs.
o Raising of platforms and guard wall of the DWs.
o Water quality testing of DWs, RWHs and SSTs.
o Outside plastering of the RWHs.
o Repairing of guttering of RWHs.