Notes on Baseline Study of a Fisheries Development Project

From the logical framework the baseline survey is a method of verification to be used with objectively verifiable indicators to evaluate the project.
Pg 10 of the proposal indicates that the baseline study is to provide data for project planning and measuring the impact of the project.
Workshop and Other Discussions
· There is an information requirement for the purpose of project planning for updated information on gher systems in Bagerhat. Information from the consultant’s reports is somewhat dated given the pace of expansion and perhaps changes in conditions, in gher systems. Further, the information in those documents came from the most developed and longest operating gher areas in Bagerhat. The ‘situation’ concerning ghers (for example, constraints, important issues, land tenure, feed, marketing, environmental factors) could be quite different in the other thanas, which have fewer ghers and a shorter history of ghers development.
· There is a requirement for information which will be used in measuring the impact  and progress of the project the project, with respect to the project participants.
· There is a desire from SDO"s viewpoint to judge or show the degree of impact the project has on households which are not participants in the project, and which are not necessarily households which have ghers.

Surveys, studies, or activities were suggested to meet these requirements
1. Situational Analysis
- as stated above, we require current information which will give us an idea whether the information we have from the consultants’ reports is still valid or whether changes, which we need to consider from a project programming standpoint, have occurred.
- information which can be used in a situational analysis can come from the case study exercise, the site selection field work exercise which are both parts of our initial traininghttp://www.ngoanddev.com/ programme. If further information is required to fill in gaps we could hire an external consultant to do this.
- the analyzed information will be given to Simon and Chris as well, so that we can judge whether project focus or logical framework changes are required.

 Socio-Economic Household Survey
- this would be a survey of randomly selected households in Bagerhat, perhaps one thana. It would be done at the outset and at year 2 (the end of direct activities with the first group of farmers).
- changes or impacts will not be attributable to the project, but to the adoption of or reliance on gher systems. If impacts on non-gher and gher households want to be examined (the purpose of the survey) a random selection would insure the inclusion of these households.
- The donor organization which is currently conducting a large soc-ec survey in Bangladesh has the thana Morrelganj in Bagerhat as one of its areas. Information from its survey may be all that is needed to satisfy the purpose of seeing which impacts the gher expansion has on communities. It would also be possible, perhaps, to have HKI tailor make a survey for this purpose if its current one is found lacking with respect to our needs. Perhaps donor or one of its sub-contractors could conduct the survey, analyze it, and report the results.
- although the information from such a survey would not be useful in examining any direct impacts of the project (although some may be inferred), it would provide information concerning the impact of gher expansion (or the new gher economy) which could be very important from a project programming view. For example, the information might indicate to the project that it should focus in a different direction(s).
3. Gher-Specific Socio- Economic Baseline Survey
- the purpose of this survey is for project evaluation; judging the impact of the project and hence would be the baseline survey for evaluation. Hence, it would include project farmers who would be surveyed at the outset and after 2 years, at the end of the project’s formal association with each household. If possible the survey could be done after another 2 years to examine the longer term impact of the project on participants.
- also, if possible, a control group of gher farmers who were not project farmers could be surveyed to provide a comparison by which project impacts could be inferred.
- the survey would be conventional in that it would collect data on social and economic indicators.
- a parallel and continuous participatory monitoring and evaluation system will be used which will insure that farmers have an opportunity to evaluate their own progress and the project’s activities with them.
- Project evaluation from these two types of evaluation techniques will give a more complete interpretation of the projects accomplishments and shortcomings.
- By using two techniques there may be a possibility of reducing the number of indicators used, i.e. eliminating redundant indicators.
- Examine other ANR projects’ conventional monitoring and evaluation indicators (and baseline surveys) and determine whether we can use some of the indicators that they have adopted in an effort to standardize between projects (and perhaps, organizations).
Impact Beyond the Project

- Donor indicated that it had no objection and would be interested in identifying impacts on nonparticipant gher households and non-gher households and examining unexpected effects on other segments of the community. It was not made clear if the impacts referred to were those related to the project, or the adoption and expansion of gher systems which has been going on for several years.
- the mission would like projects to be able to show ‘spread’ i.e. a positive impact outside of the project participants. Could this objective be accomplished as part of one of the above second or third survey outlined above?

Other Considerations
Since we are primarily interested in improving farmers’ abilities to critically consider options, problem solve, develop their own technologies..... we need some indicators to measure this. Are there any available or do we need to create some?
Debbie suggested that there would likely be some considerable advantages of combining the socio-ec and environmental monitoring and evaluation activities (in the participatory monitoring and evaluation segment of the project). In gher areas the link between environmental impacts and social consequences could be quite strong.