WHERE IS THE PROBLEM? (A Case Study)

Integrated Rural Development Organization (IRDO), an NGO has been working in Dinajpur for the last few years. It has been currently implementing two projects, one on savings and credit program and the other on social forestation program. Both of the projects have funding commitments for three years from 1994 to 1996.


IRDO received 1st year's remittance of grants for both of the projects in January, 1994 after obtaining clearance from NGO Affairs Bureau in December, 1993. It recruited its projects staff in January, 1994 and started the projects activities in full swing from February, 1994. IRDO implemented its projects activities very smoothly upto December, 1994. But in January, 1995 IRDO found that it has not sufficient money in its projects accounts to pay its projects staff salary and to meet up other projects expenses from 1995.

IRDO submitted necessary papers to NGO Affairs Bureau in late January, 1995 to obtain clearance for getting 2nd year's grants for both of the projects. It obtained clearance from NGO Affairs Bureau in late February, 1995 and then sent the clearance letters to the donors for 2nd year's remittance. IRDO received cheques from the donors in 1st week of April and the grants amount credited to IRDO's Bank Account in 3rd week of April.

During the period of 2nd year's fund releasing process, IRDO had to suspend payment of its project staff salary and also suspended the field activities.


Questions

1.     What happened to IRDO during the 1st quarter of 1995 and why?

2.     How this situation could have been avoided?